Brief on action/work plan.
Action plan was developed by the student to guide in the implementation of the practicum. Questionnaire guide for key informants was designed to capture responses from opinion leaders, district health officer and judiciary. Training and awareness materials were reviewed and used for training and awareness on human and women rights. These included; the constitution of the republic of Uganda, the local government act and decentralization policy. A report to that effect was written.
It is important to know that all the actions were implemented and reports written. The table shows summary of the actions and specific dates for accomplishments.
Action plan
-
Action Plan for implementation of the Research/Practicum Project 25th-1-2017.
Task/Activity |
Objective |
Research method to be used |
When |
Evidence/indicator |
Develop questionnaires for opinion leaders, women, etc. |
To guide and capture responses from the Key Informants (KI) |
Questionnaire |
30th Jan to 4 Feb 2017 |
Questionnaire guide |
Interview key informants on women participation in planning and decision making (NGO representatives, District Health Officer, Opinion leaders, Police, Judiciary) |
To get an understand of stakeholders in women participation in planning and decision making |
Interview method will be used. |
20th-24th Feb 2017 |
Report on the KI responses |
Review of training and awareness materials |
|
|
Week of March 2017 |
|
Awareness meetings on women’s rights using the 1995 Constitution of the Republic of Uganda and Decentralization Policy.
|
Empower women on the rights to participation and decision making using legal frameworks |
Direct Observation and listening sessions will be used |
Week 2 of March |
Minutes on awareness meetings |
Awareness creation on the Local Government Act -1997 and the Uganda planning cycle. |
Empower women on the rights to participation and decision making using legal frameworks |
Group discussion and lecture |
Week 3 and 4 of March 2017 |
Awareness report |
Conduct FGD to ascertain changes in women’s participation in planning and decision making. |
Get various opinions from stakeholders on women’s participation in planning and decision making |
FGD guide will be used. |
April to June 2017 |
Report on FGD views on any changes. |
Document, report the success, challenges and lessons learnt from the project as well as uploading report to Mahara.
|
To have documentation of the successes, challenges and lessons learnt from the project. |
July-September 2017 |
End of practicum report. |